The 90th anniversary of Shoal Lake aqueduct–ruote went over swamp, muskeg, sand and rock

By admin

Actual construction on the aqueduct began after the opening of tenders on September 19, 1914. Three major Winnipeg-based companies — Tremblay McDiarmid Company, Thos. Kelly & Sons Ltd., and the Winnipeg Aqueduct Construction Company — were awarded the contracts for the aqueduct. The first phase involved the diversion of the Falcon River, which had previously flowed into Shoal Lake at Indian Bay. The diversion was a key to the project as it allowed the development of the Indian Bay source without the need for treatment based on aesthetics (colour), ac cording to Ron Sorokowski and Duane Griffin, from the city’s water and waste department, and Chris Macey and Ken Skaftfeld, of UMA Enìgineering Ltd., the authors of the 2008 article Winnipeg’s Aqueduct.
On July 5, 1915, the Free Press re ported that prior to the diversion, the Falcon River discharged dirty-looking water into a corner of the bay, as a result of swamp water draining into the river.
Before construction on a gate house and pumping station at Indian Bay commenced large boulders at the intake site were removed by blasting and a dike was built near the entrance of the bay to divert the Falcon River.
Fuertes and Chace were on-hand when the first earth for the Falcon diversion into Snowshoe Bay was lifted by a steam shovel on June 17, 1914.
The Winnipeg Free Press on March 13,1918, reported building the 7,000 foot long (2,133.6 metre) dike required “about 230,000” yards of material, all of which was obtained from a borrow pit and quarry located at the north end of the dyke (sic).
“A large number of drainage and offtake ditches were necessary in order to drain the country properly before actual construction of the aqueduct was commenced” on May 15, 1915.
Although the route for the aqueduct was over swamp, muskeg, sand and rock, overall construction was alleviated by the fact that it was downhill for most of its length with the exception of 14 kilometres from Indian Bay. A deep cut several metres down in the rough land was made during this initial phase of the aqueduct construction.
The aqueduct was built under the Whitemouth and Falcon rivers using inverted siphons. In total, four rivers were burrowed under at six locations by using inverted siphons, a process used in Roman aqueduct construction.
The trench running the aqueduct’s length was rough-cut using steam shovels, dredges and dragline scrapers with workers trimming away the remaining 150 millimetres by hand. By the end of the project, 1.65 million cubicmetres of earth had been excavated.
Less than a year into the project, the First World War intervened. The March 13, 1918, Free Press, when reporting on the history of the aqueduct, said the war had the “effect of making it much more difficult to secure money and also causing a scarcity of labor.”
Despite the pressures of the war effort depleting the available labour pool, over 2,500 workers would be involved at the peak of the project’s construction phase.
The Free Press said over the course of the first year, 21.4 kilometres (13.3 miles) of the aqueduct were built, or 14.6 percent. During the 1916 season, 37 kilometres (23 miles) were built, so that the project was by then 41.6 per cent complete.
The method used to build the aqueduct was cut-and-cover. A one-metre trench was dug and a horseshoe-shaped conduit, averaging about 2.7 metres in height, was poured between steel forms. When the concrete cured, the forms were stripped and the pipe was covered by earth, which was necessary to prevent the water from freezing during Manitoba’s cold winters.
Every 1,524 metres, manholes were installed to allow for maintenance inspections. Surprisingly, early inspections of the aqueduct’s interior involved lowering the water level and men then boating through the sections.
“The invert slabs were poured in alternating 4.5-metre-hng sections and screeded to a smooth surface,” said the authors of Winnipeg’s Aqueduct. “Once these sections were cured, closure sections were poured. Following immediately after the completion of the invert slabs, the arch was built in 13.7-metre- long sections, also in an alternating pat tern, using an inner and outer slip form. The forms were advanced along sets of rails on the middle and outside edge of the completed invert. Several reinforced crossings were provided within the up per reaches in anticipation of future road crossings
“The specifications also required that between the walls of the trench and the aqueduct select earth backfill would be tamped carefully in 150 millimetre lifts to a depth of 1.2 metres. As the designers explained, this precaution was taken in conjunction with a. moderately light design of arch.”
However, the arch was “quite safe against the pressures of earth backfill even without packed earth at the haunches.”
A steam shovel was then used to place the remainder of the backfill over “the aqueduct to a depth of 1.2 metres in the case of solid material or 1.5 metres in the case of peaty material.”
The GWWD supplied all the cement required for the aqueduct, but contractors were charged for any wasted cement.
“All aggregate (mixed with the cement to make concrete) is supplied by the district (GWWD) and delivered to the camp sites of the contractors,” reported the Free Press. “This is obtained from gravel pits along the route of the (Greater Winnipeg) Water District rail way. Machinery is maintained at the pits to crush and mix the pit run gravel, so that the aggregate is graded in such a manner to make the densest and most watertight concrete.”
By controlling the cement and aggregate, the GWWD was ensuring the concrete used in the aqueduct was of the highest quality.
As was the case in aqueducts serving ancient Rome, water from the Shoal Lake aqueduct was channeled to a massive reservoir. At Deacon, 13 kilometres east of Winnipeg, water from the cistern was distributed via pipelines to the city and the several municipalities making up the GWWD. Over the years, the main Winnipeg reservoir has been expanded to the point that it now can hold 8.8-billion litres of water, the equivalent of a 20-day supply, according to the city of Winnipeg.
The February 1,1919, FreePressre ported figures on the performance of the aqueduct: “Eighty-five million gallons (386.4 million litres) would fill Portage Avenue between the building lines from Main Street to Sherbrook Avenue to a depth of 20 feet (six metres); the con tents of the (Deacon) reservoir … combined with the contents of the reservoir now owned by the city of Winnipeg (McPhillips), would fill this same area to a depth of 63 feet (19.2 metres), or to the height of the fourth story (sic) windows.”
Chief engineer Chace explained at a meeting of the Winnipeg Rotary Club on October 2, 1918, how the water was to be piped under the Red River. “As you know, we broke through the last portion of rock bore under the Red last Saturday night. The bore, which was made through the uneven starts of lime stone rock, will be lined with cast-iron pipe 60 inches (1.524 metres) in diameter, the joints of which will be caulked from the inside. On the St. Boniface (then a separate municipality) side this will be connected with the 66 inch (1.678.4 metres) reinforced concrete pipe forming that portion of the aqueduct; and on the Winnipeg side it will be joined up with the 48 inch (1.219.2 metres) reinforced concrete pipe running along Pacific Avenue to McPhillips Street (then the site of the only reservoir within the city’s boundaries).
“After the pipe is laid along the (24- metre-deep) tunnel, we propose filling in the overbreak, which has been fairly regular, by pouring in concrete, in its thin state, from the surface of the ground down a shaft, guiding it by pipes which can be shortened as the overbreak is gradually filled.”
The scope of the project was such that a motion picture was advertised to run at the Dominion Theatre in February, “showing the construction, engineering, works, aqueduct and district from Indian Lake (sic) right through to Winnipeg.”
The advertisement said every resident of the city should view the film to obtain “a proper understanding of the importance and magnitude of Winnipeg’s great water scheme. It ranks among the major undertakings of the world.”
By the end of March 1919, the aqueduct was essentially completed.Wesley College and Students Quarters Winnipeg MB
Wesley College Winnipeg MB

Wesley College in Winnipeg Manitoba

Actual construction on the aqueduct began after the opening of tenders on September 19, 1914. Three major Winnipeg-based companies — Tremblay McDiarmid Company, Thos. Kelly & Sons Ltd., and the Winnipeg Aqueduct Construction Company — were awarded the contracts for the aqueduct. The first phase involved the diversion of the Falcon River, which had previously flowed into Shoal Lake at Indian Bay. The diversion was a key to the project as it allowed the development of the Indian Bay source without the need for treatment based on aesthetics (colour), ac cording to Ron Sorokowski and Duane Griffin, from the city’s water and waste department, and Chris Macey and Ken Skaftfeld, of UMA Enìgineering Ltd., the authors of the 2008 article Winnipeg’s Aqueduct.

On July 5, 1915, the Free Press re ported that prior to the diversion, the Falcon River discharged dirty-looking water into a corner of the bay, as a result of swamp water draining into the river.

Before construction on a gate house and pumping station at Indian Bay commenced large boulders at the intake site were removed by blasting and a dike was built near the entrance of the bay to divert the Falcon River.

Fuertes and Chace were on-hand when the first earth for the Falcon diversion into Snowshoe Bay was lifted by a steam shovel on June 17, 1914.

The Winnipeg Free Press on March 13,1918, reported building the 7,000 foot long (2,133.6 metre) dike required “about 230,000” yards of material, all of which was obtained from a borrow pit and quarry located at the north end of the dyke (sic).

“A large number of drainage and offtake ditches were necessary in order to drain the country properly before actual construction of the aqueduct was commenced” on May 15, 1915.

Although the route for the aqueduct was over swamp, muskeg, sand and rock, overall construction was alleviated by the fact that it was downhill for most of its length with the exception of 14 kilometres from Indian Bay. A deep cut several metres down in the rough land was made during this initial phase of the aqueduct construction.

The aqueduct was built under the Whitemouth and Falcon rivers using inverted siphons. In total, four rivers were burrowed under at six locations by using inverted siphons, a process used in Roman aqueduct construction.

The trench running the aqueduct’s length was rough-cut using steam shovels, dredges and dragline scrapers with workers trimming away the remaining 150 millimetres by hand. By the end of the project, 1.65 million cubicmetres of earth had been excavated.

Less than a year into the project, the First World War intervened. The March 13, 1918, Free Press, when reporting on the history of the aqueduct, said the war had the “effect of making it much more difficult to secure money and also causing a scarcity of labor.”

Despite the pressures of the war effort depleting the available labour pool, over 2,500 workers would be involved at the peak of the project’s construction phase.

The Free Press said over the course of the first year, 21.4 kilometres (13.3 miles) of the aqueduct were built, or 14.6 percent. During the 1916 season, 37 kilometres (23 miles) were built, so that the project was by then 41.6 per cent complete.

The method used to build the aqueduct was cut-and-cover. A one-metre trench was dug and a horseshoe-shaped conduit, averaging about 2.7 metres in height, was poured between steel forms. When the concrete cured, the forms were stripped and the pipe was covered by earth, which was necessary to prevent the water from freezing during Manitoba’s cold winters.

Every 1,524 metres, manholes were installed to allow for maintenance inspections. Surprisingly, early inspections of the aqueduct’s interior involved lowering the water level and men then boating through the sections.

“The invert slabs were poured in alternating 4.5-metre-hng sections and screeded to a smooth surface,” said the authors of Winnipeg’s Aqueduct. “Once these sections were cured, closure sections were poured. Following immediately after the completion of the invert slabs, the arch was built in 13.7-metre- long sections, also in an alternating pat tern, using an inner and outer slip form. The forms were advanced along sets of rails on the middle and outside edge of the completed invert. Several reinforced crossings were provided within the up per reaches in anticipation of future road crossings

“The specifications also required that between the walls of the trench and the aqueduct select earth backfill would be tamped carefully in 150 millimetre lifts to a depth of 1.2 metres. As the designers explained, this precaution was taken in conjunction with a. moderately light design of arch.”

However, the arch was “quite safe against the pressures of earth backfill even without packed earth at the haunches.”

A steam shovel was then used to place the remainder of the backfill over “the aqueduct to a depth of 1.2 metres in the case of solid material or 1.5 metres in the case of peaty material.”

The GWWD supplied all the cement required for the aqueduct, but contractors were charged for any wasted cement.

“All aggregate (mixed with the cement to make concrete) is supplied by the district (GWWD) and delivered to the camp sites of the contractors,” reported the Free Press. “This is obtained from gravel pits along the route of the (Greater Winnipeg) Water District rail way. Machinery is maintained at the pits to crush and mix the pit run gravel, so that the aggregate is graded in such a manner to make the densest and most watertight concrete.”

By controlling the cement and aggregate, the GWWD was ensuring the concrete used in the aqueduct was of the highest quality.

As was the case in aqueducts serving ancient Rome, water from the Shoal Lake aqueduct was channeled to a massive reservoir. At Deacon, 13 kilometres east of Winnipeg, water from the cistern was distributed via pipelines to the city and the several municipalities making up the GWWD. Over the years, the main Winnipeg reservoir has been expanded to the point that it now can hold 8.8-billion litres of water, the equivalent of a 20-day supply, according to the city of Winnipeg.

The February 1,1919, FreePressre ported figures on the performance of the aqueduct: “Eighty-five million gallons (386.4 million litres) would fill Portage Avenue between the building lines from Main Street to Sherbrook Avenue to a depth of 20 feet (six metres); the con tents of the (Deacon) reservoir … combined with the contents of the reservoir now owned by the city of Winnipeg (McPhillips), would fill this same area to a depth of 63 feet (19.2 metres), or to the height of the fourth story (sic) windows.”

Chief engineer Chace explained at a meeting of the Winnipeg Rotary Club on October 2, 1918, how the water was to be piped under the Red River. “As you know, we broke through the last portion of rock bore under the Red last Saturday night. The bore, which was made through the uneven starts of lime stone rock, will be lined with cast-iron pipe 60 inches (1.524 metres) in diameter, the joints of which will be caulked from the inside. On the St. Boniface (then a separate municipality) side this will be connected with the 66 inch (1.678.4 metres) reinforced concrete pipe forming that portion of the aqueduct; and on the Winnipeg side it will be joined up with the 48 inch (1.219.2 metres) reinforced concrete pipe running along Pacific Avenue to McPhillips Street (then the site of the only reservoir within the city’s boundaries).

“After the pipe is laid along the (24- metre-deep) tunnel, we propose filling in the overbreak, which has been fairly regular, by pouring in concrete, in its thin state, from the surface of the ground down a shaft, guiding it by pipes which can be shortened as the overbreak is gradually filled.”

The scope of the project was such that a motion picture was advertised to run at the Dominion Theatre in February, “showing the construction, engineering, works, aqueduct and district from Indian Lake (sic) right through to Winnipeg.”

The advertisement said every resident of the city should view the film to obtain “a proper understanding of the importance and magnitude of Winnipeg’s great water scheme. It ranks among the major undertakings of the world.”

By the end of March 1919, the aqueduct was essentially completed.

Hotel Near the University of Manitoba

winnipeg one hour heat and air

Famouspeopleofmanitoba.ca

Blog Traffic Exchange Related Websites

categoriaUncategorized commentoNo Comments dataDecember 11th, 2009
Leggi tutto

Prelude to Arborg tax revolt Farmers’ Army leaves

By admin

Premier John Bracken should have realized the delegation in his Manitoba legis1ature office was merely the harbinger of things to come. If he had, Bracken would have listened with greater sympathy to their demands and realized desperate people are prone to perform desperate acts. Instead, the Manitoba premier dismissed the demands of the delegation representing the “Farmers’ Army” as inspired by communist agitators.

Actually, the premier had good reason to be suspicious of Communist influence. At a mass rally in Market Square on Sunday evening, speakers urged workers and farmers to unite to form a “Soviet Canada.”

The crowd gathered outside Bracken’s office in the Manitoba Legislature on Monday was stirred up into vocal resentment of the actions of the police who had prevented another mass rally that day in Market Square, as well as the presence of local labour organizers, some of whom had ties to the Communist Party.

Who ordered the presence of police to prevent the mass meeting is not revealed, but a city law prohibited such gatherings in    afternoon at the square, a throwback to the Winnipeg General Strike of 1919. The night-time mass meeting in Market Square on Sun day, October 16, 1932, went ahead as scheduled, but when the farmers and then workers applied for a permit to hold a mass meeting in the afternoon the following day, their request was re fused.

Blog Traffic Exchange Related Websites

categoriaUncategorized commentoNo Comments dataAugust 19th, 2009
Leggi tutto

Winnipeg “Wine Festival” 2009

By admin

Winnipeg Wine Festival

Special Olympics Manitoba in partnerships with Liquor Marts, proudly presents the 8th annual Winnipeg Wine Festival taking place from Sunday May 3 until Saturday May 9.

The week-long festival features fun and exciting ancillary events held through out the city from May 3 – May 6. To purchase tickets, click here.

Grape expectations – Winnipeg Free Press – WITH the eighth annual Winnipeg Wine Festival less than two weeks away, it’s high time you all get your collective butt in gear and start planning. Program guides for the Friday and Saturday public tastings should now be available, …

Winnipeg Wine Festival Matinee Tasting – May 09, 2009 (Sat): Special Olympics Manitoba proudly presents the seventh annual Winnipeg Wine Festival held from May 3rd -9th, 2009. This week long Festival will feature: Fun and exciting ancillary events held throughout Winnipeg from …

Winnipeg Wine Festival Gala Dinner – May 07, 2009 (Thu): This unique and memorable evening will be the ultimate food and wine experience. The evening begins with a wine reception followed by a five-course gourmet meal, featuring two fine wines paired with each course. …

Winnipeg : Winnipeg Wine Festival Saturday Tasting – A Collective Listing Of Food And Wine Tasting Events In Most Major Cities Around The World. Beer And Spirit Tasting Events As Well.

Wine Festival – We will be back once again to the Winnipeg Wine Festival. Be sure to visit our booth and sample some amazing wine available in Manitoba. Visit the Winnipeg Wine Festival’s website for more information.

 

A gala wine dinner on Thursday, May 7th at the Winnipeg Convention Centre and culminates with the public tastings on Friday May 8 and Saturday May 9. The matinee tasting on Saturday, May 9 from 1:30 – 4:30 pm will also return.

Tickets available for the public tastings at all Ticketmaster locations.

For more information visit www.winnipegwinefestival.com

Blog Traffic Exchange Related Websites

categoriaUncategorized commentoNo Comments dataApril 11th, 2009
Leggi tutto

Winnipeg Historic Newspaper Notes Noted

By admin

The “Winnipeg Free Press”  and the historic Winnipeg “Morning Telegram” both published papers early on in Manitoba’s history.

Notices and information in these papers might include information and notes on ways to entertain one self in early Winnipeg.  For example posts might note a hockey game at the auditorium rink , which stood at the south side of York Avenue between Fort and Garry streets.  For example the Winnipeg Victorias defeated the Montreal New Edinburghs  by a score of 5 to2,  in one series of games that wound up the following series on a following Saturday with the Victorias finally capturing the “Allen Cup”.

Again when it came to New Years day many people could be found involved in the sport of curling.  All rinks could be busy – the Strathcona , the Granite , the Civic and the Assiniboine Curling clubs were among those notable Winnipeg and Manitoba curling clubs of the day-  many still major and noted historic curling seasons in 2009.

For those not involved in sports but rather the arts – the Winnipeg newspapers of the day listed many theatres and arts attractions -  be it the “Walker Theatre” , the “Winnipeg Theatre”, or the Winnipeg “Opera House”.   One of the newest theatres of the time was  “The Orpheum”  – a brand theatre at the time – on Fort Street as well as the Empress Theatre which often carried Vaudeville shows.  Of course  performances of religious based presentations such as those held at First Baptist Church in Winnipeg could be found hosted on a regular as well as ongoing basis.

Famous People of  Manitoba

www.famouspeopleofmanitoba.ca

, , , , , , , , , , , , , , , , , .

Blog Traffic Exchange Related Websites
  • Happy Valentine's Day Happy Valentine's Day everyone! It also happens to be my birthday and since I haven't been in India on my...
  • Obama Czar Wants to Claim Your Body Parts Sunday Paper - September 6th, 2009 by Matt Cover Obama Regulation Czar Advocated Removing People’s Organs Without Explicit Consent Cass...
  • Chinese Antique Jade Antiques -> Asian -> Chinese Chinese antique jade isn't just beautiful in its own right, but carries a deep cultural...

categoriaUncategorized commento2 Comments dataMarch 30th, 2009
Leggi tutto

Canadian Museum for Human Rights – Preparations Continue to Opening

By admin

Canadian Museum for Human Rights – Preparations Continue to  Official Opening

Canadian Museum For Human Rights Near It’s Goal – The donation was motivated by the Museum’s focus on educating youth to the importance of human rights. Winnipeggers should be glowing as the Museum will bring both tourism dollars to Winnipeg, and a sense of pride in providing the world …

Famous People of Manitoba » Canadian Museum of Human Rights … – “It is an honour to be part of the ground breaking for our new Canadian Museum for Human Rights” Manitoba’s Premier Gary Doer said. “We are thrilled to hae such a worthy national institution located in Manitoba , a province with a long …

Winnipeg Free Press – New donation puts museum $2 million away from fundraising goal. Geoff Kirbyson. 2/03/2009 11:43 AM | Comments (6). Print; E–mail. Enlarge Image Enlarge Image icon. The proposed Canadian Museum for Human Rights. The Canadian Museum for …

First Exhibit Canadian Museum for Human Rights – The first exhibition for the Canadian Museum for Human Rights will be an exhibit which premiered at the Human Rights Day Youth Conference – which was organized by the United Nations of Canada , and held at the University of Winnipeg …

Construction of Canada's human rights museum - The Canadian Museum of Human Rights will soon begin construction and will open in 2012. It will be the largest human rights museum in the world.

Famous People of  Manitoba

www.famouspeopleofmanitoba.ca



Blog Traffic Exchange Related Websites

categoriaUncategorized commentoNo Comments dataMarch 7th, 2009
Leggi tutto

Breadth and Width of Manitoba History , Geography and People of World Wide Fame

By admin

It can well be said that both Winnipeg and the Province of Manitoba , Canada  have a remarkable history as well as historical record.  Indeed both can be said to have had a thriving and prosperous historical growth and record of their growth.

Whether this is the result of geography , its placement on the map , or the placement as the keystone to the growing west of Canada or to the potential of the true northern Canadian regions , none of this can be disputed.

There is no shortage of documented and archival materials both on the people , the history and the geography of the people  and the Province of  Manitoba Canada.

Winnipeg Free Press – In 2006, he wrote a short article about the 1905 meeting for Manitoba History magazine. He is one of the magazine’s editors, as well as being past president of the Manitoba Historical Society, webmaster for the MHS’s extensive website, …

Peguis deal up in air | Manitoba | News | Winnipeg Sun – I would like reperations from any one throughout history that has oppressed my ancestors. So ill need money from the English, Germans, Romans and Greeks. Im not going to hold my breath. The Natives in Canada are the only group who get …

Historic Peguis vote | Manitoba | News | Winnipeg Sun – Members living at Peguis, 200 km north of Winnipeg, and elsewhere cast ballots yesterday in a referendum on whether to accept the offer in what’s described as one of the most important decisions in the band’s history. …

 

Famous People of  Manitoba

www.famouspeopleofmanitoba.ca

Blog Traffic Exchange Related Websites

categoriaUncategorized commentoNo Comments dataJanuary 26th, 2009
Leggi tutto